This timeline shows the big milestones that are part of the Jefferson Elementary Construction project.


  • March 27, 2014, 7AM - MCSD School Board approves construction bid
  • April 13, 2014 - 9th street closed for construction, construction fence in place
  • June 1, 2015 - Jefferson Construction substantial completion
  • August/September, 2015 - Final Work
  • Late September, 2015 - Move in!